Wilmington, Delaware · Since 2021 Field-first general contractor · Mission-critical builds CareersNewsroomPrequalifyProject map
Data Centers & Industrial · 2025

Hyperscale Data Center Campus

Two data halls and a central utility yard, with every one of 72 megawatts proven before the first customer rack arrived.

Owner
Confidential
Location
U.S.
Market
Data Centers & Industrial
Delivery
Design-build
Scale
72 MW
Completed
2025
The brief

Two data halls, a central utility yard and an integrated systems test that proved every megawatt before the first customer rack arrived.

Hyperscale schedules are set by the customer’s hardware, not the builder’s calendar. This campus needed two data halls, medium-voltage distribution, generators, UPS and a cooling plant delivered in step with long-lead equipment from a dozen factories. And the owner would accept nothing short of a full integrated systems test before white space was handed over.

How we built it

The approach.

  1. 01

    Supply chain as the critical path

    Generators, switchgear, UPS modules and chillers were tracked from factory slot to setting date, with expediters visiting the plants that slipped.

  2. 02

    Skids and modules built off site

    Electrical rooms and piping skids were prefabricated and set as finished assemblies, taking weeks of field work off the schedule.

  3. 03

    White space, organized

    Hot-aisle containment, overhead busway, cable tray and fiber pathways were installed in a fixed sequence so trades never stacked in one aisle.

  4. 04

    Integrated systems test

    Load banks filled each hall to design load while utility power was pulled, generators started and UPS rode through, until every sequence passed.

The outcome.

72MW of critical capacity
2Data halls
L1–L5Commissioning, ending in a full IST
Day OneReady for the first customer rack

“A data hall is not finished when it looks finished. It is finished when we pull the utility at full load and nothing blinks.”

Commissioning lead, ScottHarry
Data Centers & Industrial

Planning something like this?

Share the project, the site and the date that matters. A senior builder will come back to you within one business day.