Wilmington, Delaware · Since 2021 Field-first general contractor · Mission-critical builds CareersNewsroomPrequalifyProject map
Perspectives

Liquid-cooled AI halls change the job, not just the equipment

Rack densities have jumped, water now runs to the row and the cooling plant is a process system. Builders who treat it like another air-cooled hall will find out at flush and fill.

April 28, 20267 min readBy Data center team

The newest AI halls do not look very different from the outside. Inside, almost everything has changed. Rack densities have climbed far past what air can carry, water now runs to the row, and the cooling plant behaves like a process system. Builders who treat a liquid-cooled hall as another air-cooled job tend to find out the difference at flush and fill.

Water is now in the white space

Direct-to-chip cooling brings a secondary fluid loop to every rack. That means coolant distribution units, manifolds and hundreds of hose connections in a room that has always been kept dry. It also means new trades in the white space, new leak detection and new rules about who may work where once the loop is charged.

The construction sequence changes with it. Piping must be cleaned, pressure tested, flushed and filled before the owner's racks arrive, and the water quality has to stay within the specification from that day on. A few hours of debris in a loop can damage equipment worth far more than the pipe.

Prefabrication becomes the schedule

On our Hyperscale Data Center Campus, power and cooling skids, pipe racks and electrical rooms were built off site and tested before they shipped. Field work became setting, connecting and commissioning. That approach pays off most in liquid-cooled halls, where piping quality and cleanliness are easier to control at a bench than overhead on a lift.

  • Set a planning grid and skid sizes that fit a truck, a road permit and a crane pick.
  • Freeze the cooling design for prefabricated elements earlier than the rest of the hall, so the shop can start.
  • Define every interface: who owns each flange, each hose, each controls point.
  • Plan flushing, filling and water treatment as schedule activities, not punch items.
  • Model rack rows, manifolds, busway and cable tray together so they share the space above the racks.

Liquid cooling moves the cooling plant into the room with the most expensive equipment on the campus. You build it like a process system or you do not build it at all.

Data center project executive, ScottHarry

Commission the loop like a critical system

Integrated systems testing for a liquid-cooled hall has to prove more than power transfers. It has to show that the loop holds temperature and flow when a pump fails, when a CDU drops out and when the electrical system changes state underneath it. Leak detection must alarm where operators will see it. The owner's team needs SOPs for connecting and disconnecting racks on a live loop.

Our advice to owners planning AI capacity is direct. Bring the builder in while the cooling strategy is still a choice, put the loop on the critical path where it belongs and make sure the commissioning plan was written for water, not for air. That is how a liquid-cooled hall is ready for operations on Day One.

Start a conversation

Let’s talk about your project.

Share the project, the site and the date that matters. A senior builder will come back to you within one business day.